We want to make improvements to the A487 at Llanrhystud.
Contents
The roads review considered this project
This page reflects our previous road investment programme. A new programme was published in the national transport delivery plan.
We will publish new scheme webpages to reflect the new programme.
Summary
Project status: planned/preliminary design (WelTAG stage 3)
Region/county: mid Wales
Start date: summer 2022
End date: spring 2023
Cost: £5.95 million
Technical advisors and designers: WSP
Registered with considerate constructors scheme: not yet
What we are doing
We want to introduce a new three-arm roundabout at the southern extent of Llanrhystud. A Differential Acceleration Lane (DAL) is also proposed in the southbound direction off the new roundabout on the A487 towards Aberaeron.
Why we are doing it
We have identified a need to undertake safety improvements at existing junctions along the trunk road network.
Current progress
The scheme is reaching the end of the preliminary design stage. A WelTAG stage 3 report is being produced.
Timetable
Award of consultant: winter 2016
WelTAG stage 1: 2017 to 2018
WelTAG stage 2: 2018 to 2019
WelTAG stage 3: 2020 to 2021
Preliminary design and preparation of orders: 2021
Detailed design: 2022
Construction: summer 2022 to spring 2023
How we are consulting
We are currently running a .
Next steps
We will consider the consultation responses. Following this we will recommend preferred changes to the scheme by summer 2021.
Detailed design will begin in late 2021.